THE END IS IN SITE

THE END IS IN SITE

With the end of the construction job in sight it is nearing the time when timber

will reach the Bin Sorter. By the end of November we will see the installation of the

transfer conveyor which will signal the connection of the structure back to the

existing sawmill.

Services (electrical, pneumatic, hydraulic) will also be nearing completion at this

time with some aspects of the machine having already been given a trial run

with great success.

The project is still a hive of activity however it’s all coming together very quickly

with an initial run testing phase hopeful before Christmas.

“It’s probably been close on 4 years since some of the bin sorter equipment

has run, we originally saw it in Australia back in Nov 2008 decommissioned and

imported it early 2009 so it’s certainly been a while and an exciting time now

seeing it come back to life” Andrew Anderson, Project Manager.